The calendar
- September–October: photos on WhatsApp, site visit, written quote.
- October–December: the engineer prepares the approval, we order liner and equipment.
- Winter: digging, frame, pipes, liner, whenever the weather allows.
- Before Easter: filling, water balancing, lighting, deck.
- Spring: photos for the booking platforms, by day and by night.
What delays a project
- A request that arrives in March: the time for paperwork and building gets tight.
- Design changes after the liner is ordered.
- Water for the first fill not booked in time, especially on islands.
- Power for the plant room not planned.
Photos that bring bookings
The first photos go up on the platforms before the first guest arrives. An overflow pool with clear, still water, shot in the morning and again at dusk with the lights on, gives two different pictures from the same spot.